Schedule Performance Of Construction Project By Using Weibull Analysis

  • Author(s):

    Akash G. Charbhe | Prof. A. A. Suryavanshi | Prof. Sudhanshu Pathak | Prof. S. V. Pataskar

  • Keywords:

    Construction; Cost Control; EVM; Schedule Performance; Weibull Analysis.

  • Abstract:

    In Every Project, Construction Managers Regularly Monitor Projects To Ensure That The Project Performance Is Under Control. Traditionally, The Earned Value Method (EVM) Is Widely Used Tool To Control And Monitor Schedule Performance Using The Schedule